THE ECONOMICS OF HARDFACING
1.1 General
The importance of hardfacing is widely recognized. There are many documented instances of savings that have been made in many industries by the use of hardfacing.
However, this does not imply that hardfacing is best in all instances and an analysis of the costs involved in hardfacing and other alternatives should be made. The accurate calculation of costs involved may be quite complex, as many factors must be considered to determine whether hardfacing is cost effective.
This section explains in detail the factors involved in costing. It is necessary that these factors be understood since their importance will differ from job to job and from workshop to workshop. Labor and overhead will always be major costs and will vary depending on company, size, complexity, technology level and type of output.
The design or geometry of the original component will determine the amount of weld deposit required and ease of applying it.
The highest deposition rates are achieved in the flat and horizontal positions.
The welding process and process parameters (procedure) chosen will govern the time required as determined by deposition rate, deposition efficiency and operator factor.
Additional costs associated with the work such as transportation, machining, heat treatment and inspection.
|
Current/Amps Stick Electrode Semi-Automatic Submerged Arc |
|
110 1.8
- - |
|
125 2.0
- 3 |
|
150 2.6
- 4 |
|
175 3.0
6 4 |
|
200 3.7
8 6 |
|
225 4.2
10 8 |
|
275 7.0
12 10 |
|
325 9.0
14 12 |
|
375 -
16 14 |
|
425 -
18 17 |
|
475 -
- 20 |
|
525 -
- 24 |
Deposition efficiency is expressed as a percentage and is determined by dividing the weight of metal deposited by the weight of the consumable expressed as a percentage. Efficiencies will vary with process as shown in Table 1.1.B.
|
Process Deposition Efficiency % |
|
Manual (flux-coated electrode) 60-70 |
|
GTAW (TIG) 95 |
|
GMAW (solid and metal-cored) 95 |
|
FCAW (open-arc or gas-shielded) 85-90 |
|
SAW (submerged arc) 90-95 (wire only) |
|
Gas Welding (bare rod) 95 |
Operator factor or efficiency is expressed as a percentage and is the effective deposition hours divided by total hours expressed as a percentage. Time study methods or arc monitors are used to determine the operator factor and some typical factors are shown in Table 1.1.C.
Table 1.1.C. Operating Factors
|
Process Operating Factor % |
|
Manual 30 |
|
GTAW 20 |
|
GMAW 60 |
|
FCAW 60 |
|
SAW 65 |
*Semi automatic processes
Activities that affect the operator factor include: preparation, setting up, idle time, instruction, crane time, preheating, deslagging, operator skill and degree of automation.
1. Flux Cost (submerged arc welding only) per lb of weld metal deposited
Unit Price ($/lb) x Consumption Rate (lb/hr) ÷ Deposition Rate of Wire (lb/hr)
2. Shielding Gas Cost (gas shielded processed only) per lb of weld metal deposited
Unit Price ($/ft3) x Flow Rate (ft3/hr) ÷ Deposition Rate of Wire (lb/hr)
Example:
Argon/CO2 @ $.15/ft3
Flow Rate of 30 ft3 per hour $0.15 x 30 = $.64/lb
Deposition Rate of Wire @ 7 lbs/hr 7
3. Power Cost per lb of weld metal deposited
[Unit price ($/kw hour) x kw per hour]÷ Deposition Rate (lb/hr)
Kilowatts = (welding volts x welding amps) ÷ 1000
Voltage @ 21
Current @ 200 amps $0.126 x 4.2 = $.08/lb
Deposition Rate of Wire @ 7 lbs/lb 7
4. Welding Material Cost per lb of weld metal deposited
Wire/Electrode Price ($/lb) ÷ Deposition efficiency (%)
Example Welding Wire @ $5/lb $5 = $5.26
Deposit Efficiency @ 95%
.95
5. Labor Cost per lb of weld metal deposited
Labor Charge ($/hr) ÷ [Deposition Rate (lb/hr) x Operating factor (%)]
Example Labor Cost @ $25/lb $25
= $5.95/lb
Deposition Rate @ 7 lbs/hr 7
x .60
6. Overhead Cost per lb of weld metal deposited
Overhead price ($/hr) ÷ [(Deposition Rate (lb/hr) x Operating factor (%)]
Example Labor Cost @ $10/lb $10
= $2.38/lb
Deposition Rate @ 7 lbs/hr 7
x .60
Operating Factor @ 60%
7. Total Cost per lb of
weld metal deposited
Flux Cost + Gas Cost + Power Cost + Material Cost + Labor Cost + Overhead Cost
8. TOTAL COST OF HARDFACED COMPONENT
Width of hardfacing (in) x Thickness of hardfacing (in) x Length of
hardfacing (in) x
Total cost/lb (7 above) x 0.3 = Total
hardfacing cost
· Metric
Equivalent - Width of hardfacing (cm) x Thickness of hardfacing (cm) x
Length of
hardfacing (cm) x
Total cost/kg (7 above) x .008 = Total hardfacing cost
This calculation provides the means to determine the total cost of depositing a hardfacing layer of a given thickness based on a given width and length, with the deposited cost per pound previously determined.
1.3
Cost Advantage
The determination of the cost advantage of hardfacing over replacement enables management to reach an informed decision on whether to hardface a particular component.
OPN OPR
PCN = Prime cost of new component = Cost of new component + downtime cost (new)
PCR = Prime cost of hardfacing ($)
OPN = Work output during life of new component
OPR = Work output during life of hardfaced component
Where there is a positive cost advantage, hardfacing is likely to be the best solution, and an indication of the annual cost savings can be determined.
This simple equation for cost advantage does not take into account factors such as plant depreciation and replacement, cost of capitalization, taxation benefits, and other factors that may affect the decision.
Most of the data needed for the above calculation is relatively easy to obtain and will be available as predetermined costs in many shops. The cost of hardfacing can be calculated using the method shown in Table 1.3.
Other factors may require consideration, such as the value of work output for the hardfaced component which may not be known and has to be estimated initially.
1.4. Annual Cost Savings and Extra Expenditure
Where significant extra expenditure is required to implement a new hardfacing repair method which has a positive cost advantage from equation 1, a supporting case will normally be required by management. Data required will include the annual cost savings and extra expenditure.
The annual cost savings (CS) expressed in $/year by using hardfacing instead of a new component is given by equation 2:
Equation 2: CS = CA x PR
CA = Cost advantage from equation 1 ($/unit output).
PR = Production rate (Averaged over the year including downtime, and here
assumed equal for both new and repaired components) (unit output/year).
Example 1 – Shear blade for Cold Punching ¾” (18 mm) Mild Steel
Blade cost =$100
Installation cost =$20/hr x 0.5hr = $10
Downtime cost =$210.00/hr x 0.5hr = $105
Prime cost - new =215
Work output - new =2000 cuts
Cost per cut =0.1075
Hardfaced Component
Cost of hardfacing (see 1.2) =$60
Installation cost and downtime cost =$115 (same as new component since a second blade had already been hardfaced.
Prime cost - hardfaced =175
Work output - hardfaced =11,500 cuts
Cost per cut =0.0152
Cost Advantage (CA) = 215 - 175 = 0.1075 - 0.0152
2000 11500
Note: The figures shown are hypothetical.
This shows a positive cost advantage, meaning hardfacing is beneficial. A reduced prime cost for the hardfacing method contributes to this advantage, but the increased work output is the major contribution.
If the usage of the shear blade increases to 46000 cuts per year the savings increases as follows:
= 0.0923 x 46000
= $4246 (i.e. annual saving by using hardfacing instead of new component).
At the exit from the furnace is the clinker crusher, on which the hammers had to be changed every month. The shutdown of this crusher to change the set of 36 hammers caused a production shutdown lasting 2 days.
· Cost of Lost Production:
2 days at 1000 tons/day and $17 per ton $34,000
· Cost of Set of 36 hammers:
Cost of 36 hammers
$450.
· Labor and overhead $300.
· Total cost of machine downtime $34,750.
Annual loss through 12 shutdowns $417,000.
After a careful study, a hard overlay using a continuous wire was applied and enabled the service life of the hammers to be prolonged by 100% - i.e. from one to two months. Downtime and production costs were halved and productivity increased.
· Cost of lost production: $34,000 x 6 = $204,000
· Cost of hammers: ($450 + $300) x 6 = $4,500
· Cost of hardfacing overlay: $550 x 6 = $3,300
· Total annual cost: $211,800
Total annual saving: ($417,000 - $211,800) $205,200